A major project to bring Metro-North trains to Penn Station and open four new stations for the commuter line in the Bronx is at least three years behind schedule, MTA officials said Monday, blaming ...
Metro-North wrapped one of its locomotives in a design that honors the Armed Forces on Veterans Day. It will be displayed at Grand Central Terminal.
Full Metro-North service in the East Bronx will be delayed again, this time until 2030, as Amtrak and MTA continue to joust over the project’s schedule, transit officials said Monday. But MTA brass ...
Starting next spring, on a date not yet announced, trains will again run on a regularly scheduled basis between New York City ...
The Metropolitan Transportation Authority announced the completion of station and accessibility upgrades at the St. Albans ...
11don MSN
Amtrak boss blames MTA’s ‘wounded pride’ as transit agency claims major Penn Station project delays
The head of Amtrak said “wounded pride” is fueling the MTA’s smear campaign against the federal train company after the MTA ...
A $2.9 billion commuter rail project to connect New York City’s northern suburbs to Pennsylvania Station faces a three-year delay, according to the Metropolitan Transportation Authority.
The MTA said the Metro-North Bronx expansion project will not be completed until 2030 at the earliest due to Amtrak refusing to close its tracks for work.
The completion of a $2.9 billion project to connect the Metro-North Railroad to Penn Station is facing a three-year delay, with MTA officials on Monday blaming their partner on the project, Amtrak, ...
New daily round trip will restore direct service between Grand Central and Albany-Rensselaer for first time since 1967.
The U.S. Department of Transportation (USDOT) on Oct. 30 reported reaching three “key” milestones for the Penn Station New ...